BM522 Project Management – CW1 Individual Project Report: The Regent House Hotel Digital Guest Check-In Project

UniversityBuckinghamshire New University (Level 5, C23 framework)
ModuleBM522 Project Management
AssessmentCW1 – 1,500-word individual project report
Weighting50%
DeadlineSaturday 14 November 2026, before 2:00 pm
AI statusNon-secure: reasonable and appropriate AI use permitted

BM522 CW1 gives students a ready-made project and a full activity list, then asks them to plan it like a project manager: business case and SMART objectives, a network diagram with the critical path, a Gantt chart, stakeholders, a WBS, a risk register and quality criteria.

Project Scenario (summary)

The Regent House Hotel is a privately owned 85-room boutique hotel in Belfast serving business travellers and weekend tourists. Manual paper registration, identity checks, payment verification and key allocation cause long queues between 3 pm and 6 pm on Fridays, Saturdays and event dates. Management has approved a digital guest check-in and check-out system with pre-arrival registration, secure ID upload, payment confirmation, digital or kiosk room access, self-service check-out and automated receipts. Scope includes platform procurement and configuration, integration with the Property Management System, kiosks or tablets, staff training, a GDPR and data security review, pilot testing and full rollout.

  • Start: Monday 11 January 2027; full rollout before the summer season, within six months
  • Indicative budget: £180,000; minimum disruption to hotel operations
  • Key risks: integration issues, staff resistance, guest data privacy, supplier delays, cybersecurity and front-office disruption
  • Team: general manager, front-office manager, IT support, finance manager, data protection officer, external software supplier, reception staff representatives and pilot guest users

Activity Scheduling Information

IDTaskDaysPredecessors
1Approve project mandate and appoint project manager2–
2Review current front-office process and identify requirements71
3Prepare business case and project initiation document52
4Obtain approval from hotel senior management23
5Prepare supplier specification and request for proposal44
6Invite suppliers and receive proposals105
7Evaluate proposals, select supplier and negotiate contract86
8Complete contract approval and procurement sign-off37
9Conduct technical assessment of existing hotel systems54
10Design digital check-in process and guest journey64
11Configure digital check-in software108, 9, 10
12Integrate system with existing Property Management System811
13Complete GDPR, data security and payment compliance review611
14Install guest self-service kiosks and/or tablet devices68, 9
15Conduct internal testing and resolve technical issues1012, 13, 14
16Develop operating procedures and train front-office staff710, 15
17Run pilot launch, review feedback and implement improvements1216
18Full system rollout and project closure report417

All durations are working days (Monday–Friday, eight hours per day; weekends excluded, public holidays ignored). Network diagram calculations use the day 0 convention.

Coursework Tasks

  1. Task 1 – Business case, project objectives and methodology [15 marks]: business need and aim, three SMART objectives, deliverables, milestones, outcomes and benefits, time/cost/operational constraints, and a briefly justified planning approach.
  2. Task 2 – Network diagram, critical path and Gantt chart [25 marks]: (i) a network diagram showing all activities, dependencies, durations, ES, LS, EF and LF, with the critical path highlighted and the shortest completion time stated; (ii) a Gantt chart in MS Project or an approved tool showing sequence, dependencies, dates and milestones.
  3. Task 3 – Stakeholder analysis and communication strategies [20 marks]: at least five internal and external stakeholders on a power/interest matrix, their expectations, concerns, influence and likely conflicts, plus a communication plan in the appendix.
  4. Task 4 – Work Breakdown Structure [10 marks]: a clearly numbered, deliverable-oriented WBS (not a chronological activity list).
  5. Task 5 – Risk analysis: a risk register with mitigation strategies for the five highest-priority risks.
  6. Task 6 – Quality: five quality requirements with acceptance criteria, specifications and control measures.

Need help with your BM522 network diagram and critical path?

Order Non Plagiarized Assignment

The post BM522 Project Management CW1 Assignment Brief 2026-27: Regent House Hotel Digital Guest Check-In Project Report | Buckinghamshire New University appeared first on Students Assignment Help UK.

Academic Writer & Editor
WhatsApp